What is work study (Activity timing and Method Study)


Work study; activity timing and method study are an important part of any lean manufacturing implementation if you wish to design manufacturing cells or balance and improve existing flow lines and cells.

Traditional work study usually involves the use of an industrial engineer standing over an operator with a stop watch to time the operations involved in producing a product to measure standard times for costing and payment. These times would be used to estimate costs for products and to set production targets that could be used to either reward or penalize the workforce.

Methods used within lean manufacturing try to avoid some of the problems associated with these traditional methods by including the workforce in taking these measurements and using them to help drive continual improvement.

Method Study

Work Study
See all 2 photos
Work Study

Work Study Video

Traditional Workstudy problems


There were many problems with the traditional methods of work study or the dreaded "time and motion" studies;

They used an “expert” who’s opinion of what should be done and how could often be at odds with the people who actually did the work and so often failed to make improvements to the process.

Their appearance with their stop watches caused an immediate change in behavior by the operators (usually slowing down to ensure that targets were not set too high!)

The targets set were average measurements – 50% of operators would be slower and 50% faster – but management would expect everyone to meet the production targets. In practice the slower people would fail to meet targets set and the faster more able operators would slow down to only produce the target causing an actual reduction in output!

Where incentive schemes were introduced for exceeding targets the operators would often take “short cuts” such as failing to do quality checks to try to gain bonus leading to higher levels of rejects at the customer.

Industrial Engineering

Lean Time and Motion Studies

Post-it Notes, 3 in x 3 in, Ultra Collection, 14 Pads per Pack
Post it notes to make notes for your study, use different colors for waste, and value add.
Amazon Price: $14.50
List Price: $24.49
ACCUSPLIT Survivor Stopwatch with Clock and Extra-Large Display
Stopwatch for your activity timings
Amazon Price: $7.49
List Price: $11.45
Toshiba Camileo H30 Full HD Camcorder - Silver/Black
Simple video camera to record your processes and download to computer for review by the team.
Amazon Price: $143.99
List Price: $249.99

Activity Timing for Lean Manufacturing


With lean we try to simplify the activity timing as much as possible, we also try to identify the individual work elements and identify them as either adding value or as being non-value adding and wasteful steps to be eliminated or reduced.

Lean manufacturing tools are team tools, by this I mean they should not be used by an expert who comes to town to implement their changes on the workplace; they are for the use of the people involved in the workplace to help them create and agree their own improvements through the use of 5S, Kaizen, smed and a host of other lean manufacturing tools.

So rather than have an industrial engineer stood over the workforce using a stop watch or even the team watching other members with stop watches we can use video to record the process during each shift. Each operator should understand that we are trying to make the process easier and more efficient not just for the companies benefit but for the operators benefit also. The method study and activity timing is undertaken by the team as a whole not by an outside expert.

The video should cover each shift and each operator; the team can then use the video to view differences in methods and to time the elements of each operation as well as identify them as being value adding or non-value adding.

Work elements are the individual steps of the process, picking up a component (non-value adding), loading a fixture (non-value adding but maybe unavoidable), operating the press (value adding), and so on.

Each should be timed at least 10 times to the nearest second and the time used should be the lowest repeated time; so if the operation took – 10, 13, 12, 12, 11, 14, 13, 12, 15, 14 we would select 12 seconds as the lowest repeatable time. Comparisons should be made between operators and between shifts to identify differences in methods used. Elements in which something goes wrong should not be included within the study.

As per 5S the best possible method should be documented on a standard operating instruction to ensure that they are maintained across all shifts and employees and as an aid for training.

Using Work Study

Activity timing Yamazumi chart
Activity timing Yamazumi chart

Continuous process improvement


By identifying each work element as being either value adding or non-value adding we have an opportunity for the teams to either totally eliminate the non-value adding steps or to reduce them making their processes more efficient and also easier and safer for themselves.

They can also create additional improvements by considering the work method study itself and comparing between shifts and individuals to find the most efficient way. These methods can be used within your kaizen teams to ensure continual improvement of processes.

Cell Balancing using Activity Timing


By taking measurements of each work element you are able to review the entire process in line with the customer demand rate or Takt time. By using a tool known as a Yamazumi chart you can balance the work elements of a process between the operators to ensure the optimal number of operators and machine utilization to achieve customer demand.

If one operator has too many work elements and their total time exceeds takt time we can give some of these elements to the operators that either precede or come after them to balance the amount of work between all of the operators in the cell. We aim to achieve around 95% of Takt time for each operator.

This can often mean slowing down some jobs within the process which may seem the wrong way to approach improving efficiency, but the slowing of these processes prevents the buildup of inventory and all of the associated wastes and costs.

Method Study


If you have any questions regarding Work study, activity timing and method study or about lean manufacturing tools and techniques in general please leave them below.

Comments

Madhumita 6 months ago

Time & motion study where do can we use?

LeanMan profile image

LeanMan Hub Author 6 months ago

Madhumita, thank you for commenting; I am not 100% sure what you are asking, but if you asking where you can use a time and motion study the answer is anywhere that work is done! I hope this is what you want to know, if not please clarify your question about work studies and activity timing and I will give you as best an answer as I can.

Jaysie profile image

Jaysie 6 months ago

Hi good day! Mr LeanMan as i read your hub here ill become more aware about the culture of people living in Middle eastern most specially in Saudi Arabia..

I love to read it because it can help to all of us here specially for those people who wants to work in middle east, like me it helps alot!

MrleanMan im sorry i need your help i just wanna ask some question just need your opinion. I was in UAE from 2007 to 2011 but sad to say that there's something happened to me i met 1 local guy there and the reason why i met him because we need to talk about the job offer but that job offer turns to deportation coz this arab guys he ask me to do w sex w him inside the car but i refused because of that he gave me problem ill make it short they accused me catch me and they deport me to my country i cant comebk coz i had eye scan and finger prints now i have LIFETIME BAN in uae.

I want to ask do you think my lifetime UAE ban is applies to all gcc countries ??? coz i have too many offers going gcc countries now i want to work in saudi and i feel afraid that maybe becuase of my ban, i might have problem if ill work gcc pls help me if u know something about ban

thanks and advance...

LeanMan profile image

LeanMan Hub Author 6 months ago

Hi jaysie,

It is nice that you have taken the time to read some of my hubs, however you have chosen to ask questions about a completely different subject to this hub; work study; method study and activity timing and time and motion studies.

I have replied to you via email.

Ante 3 months ago

Hi Mr. LeanMan,

I would like to know, how should a time study be conducted in a work station where there are more than 1 operator. If for example, there are two operators in a workstation having 3 tasks A, B and C, these operators can say help each other to finish task A and designate tasks B and C to each one of them.

Thank you very much!

LeanMan profile image

LeanMan Hub Author 3 months ago

Hi Ante, that is a great situation to have, you can observe any differences between how the different operators do the individual tasks and help them to document and put in place the best methods. Video and time from the video the individual elements of the tasks as performed by each operator.

Ante 3 months ago

Thanks very much.

Is video recording a common method for taking time study? I am concerned about how operators will react with that. They might be uneasy...

Thanks again.

LeanMan profile image

LeanMan Hub Author 3 months ago

Ante, if you are planning to improve the process with the involvement of the operators involved in it I have never had any problems with getting their buy in and in fact having them doing the timings from the videos. We are not trying to get them to work faster but to help standardise and improve the process to make it easier for them.

BONGANI 3 months ago

If a mananger ask me, What will your time study approach be when conducting your time studies? what is the positive approach

LeanMan profile image

LeanMan Hub Author 3 months ago

Thanks for reading Bongani, it is your reason for conducting time studies that is the important factor - if your approach is to get more out of your operators then you are unlikely to get any support from them as they will resent you trying to make them work harder. If however the aim is to improve the workflow and to simplify and improve the processes to make their work easier then they should hopefully support the process.

wangqi 2 months ago

LeanMan? What is your nationality?

LeanMan profile image

LeanMan Hub Author 2 months ago

Hi Wamgqi, I am from the UK but currently living and working overseas.

Submit a Comment
Members and Guests

Sign in or sign up and post using a hubpages account.



    • No HTML is allowed in comments, but URLs will be hyperlinked
    • Comments are not for promoting your Hubs or other sites

    Please wait working